When should permanent control measures be installed during the construction schedule?

  1. As late as possible

  2. As early as possible

  3. Within two weeks

  4. Just before final inspection

The correct answer is: As early as possible

Permanent control measures should be installed as early as possible during the construction schedule to prevent erosion and sedimentation from the outset of the project. Early installation allows these measures to effectively manage stormwater runoff throughout the construction phase, minimizing potential environmental impacts. By integrating permanent controls early on, the site can better handle storm events, reducing the risk of soil loss and sediment discharges into nearby water bodies. This proactive approach not only helps in compliance with stormwater regulations but also can lead to cost savings in the long run, as it reduces the need for additional temporary measures and minimizes the impacts that could arise from uncontrolled runoff. Early implementation demonstrates a commitment to environmental stewardship and can facilitate smoother transitions to final project completion and maintenance.