Owners of projects disturbing five acres or more must submit which document to the MDNRE?

  1. Environmental Impact Statement

  2. Storm Water Management Plan

  3. Notice of Coverage (NOC)

  4. Compliance Certificate

The correct answer is: Notice of Coverage (NOC)

For projects that disturb five acres or more, it's essential for owners to submit a Notice of Coverage (NOC) to the Michigan Department of Natural Resources and Environment (MDNRE). The NOC serves as a formal acknowledgment that the project is covered under the National Pollutant Discharge Elimination System (NPDES) permit requirements for stormwater discharges associated with construction activity. This requirement is part of the efforts to manage and mitigate the potential impacts of stormwater runoff resulting from construction, thereby protecting water quality. Submitting an NOC ensures that the project adheres to regulatory frameworks, establishes compliance with state and federal laws, and highlights the commitment of the project owner to implement best management practices for stormwater. Without this document, construction might proceed without adequate consideration of environmental protections, leading to potential violations of stormwater regulations. The other documents mentioned, such as Environmental Impact Statements and Storm Water Management Plans, serve different purposes. While an Environmental Impact Statement assesses the potential environmental effects of a proposed project, it is not a submission requirement solely based on the area disturbed. A Storm Water Management Plan is a crucial component that might be included in the submission but does not replace the requirement of the NOC. Finally, a Compliance Certificate indicates adherence